Wheatley Updates

This page will act as a resource page for Wheatley's Revitalization project.


This page will act as a resource page for Wheatley's Revitalization project.


  • Wheatley Drilling Update

    UPDATE: Drilling operations continue. Due to some logistical problems with acquiring services and materials, our projected date for the drilling equipment to move out is extended to October 23rd. After this date you may see other Chatham-Kent equipment working on the site to complete fencing, topsoiling and seeding.

    At 6:00 pm on Saturday the surface casing was successfully installed and cemented into place. This installation will greatly contribute to the overall safety of further operations. The blow out preventer will now be installed prior to drilling deeper into the well. It is our belief that we are still tracking the original wellbore that was probably drilled between 1890 and 1910 and subsequently abandoned in the 1930s. While we are drilling deeper we will be conducting many tests, including; gas, geologic and pressure analysis.

    We continue to watch for any changes in the monitoring well. Currently the monitoring well has stopped venting any gas, including H2S. Ongoing testing of the monitoring well and other wells that were previously abandoned on the site will further our understanding and help to confirm if we have been successful in stopping the gas migration.

  • Community Meeting for Wheatley Investigation

    Following the discovery of a potential petroleum well found in downtown Wheatley, the Municipality of Chatham-Kent is hosting a community open house for Wheatley residents tomorrow September 24th from 2pm-3pm at the Wheatley Village Resource Centre.

    Municipal representatives and consultants will be on hand to explain technical details and answer any questions. Materials will be posted on the Let’s Talk Chatham-Kent Wheatley Emergency Webpage for those who cannot attend, located at www.letstalkchatham-kent.ca/wheatley-updates.

    Part of the conversation will be around the operational plan instigated by the investigation project team that will involve bringing the contracted drilling rig to the site to further investigate the potential petroleum well found. The mobilization of the rig will bring much more activity to the site including noise and light, once drilling operations begin, they will operate 24 hours per day 7 days per week as communicated during the last public meeting.

  • Possible Petroleum Well Found at 17 Talbot St. East

    The project team has found what they believe is a wooden-cased petroleum well on the site of 17 Talbot Street East underneath the cement floor. No hydrogen sulfide gas has been detected but small amounts (300ppm) of methane can be detected.

    The team is assessing next steps and will be following the operational plan. The venting hood will be placed over the well when practical as an extra precaution.

    At this time there is no risk to the community from this finding. The immediate next step will be to install a conductor pipe over the well and bring it back to surface. Once further details are known they will be communicated.

    Chatham-Kent Fire & Rescue Services as well as Chatham-Kent EMS remain on site at all times to ensure the safety of the site and the surrounding community.

    Updates continue to be posted on the Let’s Talk Chatham-Kent Wheatley Updates webpage, located at www.letstalkchatham-kent.ca/wheatley-updates. Residents are encouraged to check back often as information on progress and future schedules will be posted here.

  • Further Update on the Final Phase of the Wheatley Investigation

    The final phase of investigation in downtown Wheatley is nearing completion, with contractors having investigated roughly 75% of the affected properties. Work is currently underway at the site of 15 Talbot Road East and will continue east towards 23 Talbot Road East property in the coming days.

    To date, there have been no active gas wells discovered. On September 18, excavation activities uncovered a historic brick structure with a 2” pipe in the middle immediately beneath the cement slab of 15 Talbot Road E. No natural gas was detected in the hole or pipe. Equipment was mobilized to evaluate the depth and type of well. On September 19, further excavation revealed the depth to be approximately 4 meters below grade, and native soil was located at this depth indicating that no deep well is present. Backfilling of the area will continue. Once backfilling is competed the excavation activities will continue as per the original plan.

    The investigation work will continue at least into next week, and should anything substantial be found, work will continue after that to address any issue present. Chatham-Kent Fire & Rescue Services as well as Chatham-Kent EMS remain on site at all times to ensure the safety of the site and the surrounding community.

    Media releases will only be posted in the event of significant milestones or if pertinent information needs to be communicated to the public.

  • Updates on the Final Phase of the Wheatley Investigation

    Many people in Wheatley have been asking about our progress on the site. Here are a few pictures to give you some idea where we are. The first picture shows the site after APEC’s 1, 2 and 3 were located and abandoned and after the installation of the scrubber that is housed in the sea can. Picture 2 shows after all the buildings were demolished. Picture 3 shows the site immediately prior to work staring on September 3rd. Picture 4 shows our progress to noon on Thursday September 12th. We started our work at 37 Eire and are currently on 9 Talbot. We are making good progress.

    People are curious about how we will know when we locate a well. We had some excitement on Tuesday this week when we found a round hole buried behind 23 Eire. We eventually concluded that the feature was an old privy. The photographs show what we found and the progression of determining what the feature was. When we first come across an interesting feature, we take gas samples to determine if the gas is from a biological source (like an outhouse or rotting vegetation) or a thermogenic source (deep in the earth where oil and gas is produced from). In this case we determined the source as biological and continued to excavate until we came to the bottom of the feature. If we found a thermogenic source, we would secure the gas flow to ensure we have no dangerous emissions, then proceed to determine what kind of well we have encountered, a gas or water well.



  • Emergency Exercises Taking Place During Investigation Work

    As part of the final phase investigation currently taking place in downtown Wheatley, emergency exercises are being conducted on site.

    These are mock emergency scenarios being conducted as a part of training for staff on site to practice responses to several potential emergency situations.

  • Elm Street to be Closed Temporarily During Investigation Work

    As part of the final phase investigation currently taking place in downtown Wheatley, equipment has been staging at the work site throughout the week.

    This equipment requires additional space for storage, and as a result, the roadway and sidewalk between 22 Elm Street and the corner of Elm and Erie Streets has been added to the work site and will be closed to all vehicle and pedestrian traffic until the work has been completed.

    This closure is a temporary necessity, and the road and sidewalk will reopen once the investigation work is completed. We apologize for any inconvenience this may cause.

  • Wheatley Public Information Package

    The Wheatley Public Information Package provides critical updates on safety measures, current developments, and preparation guidelines as part of the town's ongoing recovery efforts.

    You can access the full package here: Wheatley Public Info Package

  • Wheatley Investigation Update

    On July 15th, Council passed staff recommendations to procure the services of ELM 360 Environmental Consulting Ltd. to implement the next stages of the Downtown Wheatley Investigation. The report and video can be reviewed on the Municipality’s website:

    https://pub-chatham-kent.escribemeetings.com/Meeting.aspx?Id=dd35617b-942b-4f67-a5e6-84028649f916&Agenda=Agenda&lang=English&Item=78&Tab=attachments

    On site work is anticipated to begin on September 3rd with preparatory work already underway. As discussed in the council report, the excavation of the current evacuation zone is to confirm or deny the existence of any more water or gas wells on the site and to remove the remaining foundations of the buildings. Chatham-Kent along with the contractors have developed an extensive Emergency Response Plan to cover any scenarios that could be encountered during the work. This plan includes having all staff and equipment on standby prepared to work 24 hours a day to remediate a gas well if found.

    Chatham-Kent representatives will be starting this week a door-to-door campaign informing residents in proximity to the work site as to what they can expect in the coming months and to educate about the emergency response plan. A community open house will also be held August 8th from 6pm-8pm at the Wheatley Village Resource Centre where municipal representatives and consultants will be on hand to explain technical details and answer any questions. Materials will be posted on the Let’s Talk Chatham-Kent Wheatley Emergency Webpage for those who cannot attend.

    As part of the work plan, 360 Engineering and Environmental Consulting will be flying a drone capable of detecting methane emissions over the village and surrounding rural areas. This work will be done pre and post excavation in the work zone to confirm if any activities caused a change in known methane emissions. The drone will start flying on August 7th and is anticipated to take several days to complete.

    Also at the July 15th meeting council approved the purchase of 17 Elm Street in Wheatley. The vacant lot will be used as a temporary staging and meeting area for staff and contractors during the excavation work. Residents can expect to see the site being prepared for office trailers over the coming weeks. After the project is complete, future uses for the property will be further reviewed and considered.

    For updates and more up-to-date information on the Wheatley project, visit the Chatham-Kent Let’s Talk page at https://www.letstalkchatham-kent.ca/wheatley-updates


    -ends-

    Media Contact:

    Eric Labadie
    Manager, Corporate Communications
    Municipality of Chatham-Kent
    519-360-1998 x 2039
    ericl@chatham-kent.ca

  • Business Mix Analysis

    What it is: This is an in-depth look at the variety of businesses in downtown Wheatley. It helps us understand what we have, what we’re missing, and what could be improved. The analysis doesn’t just count shops and services; it digs into how they’re doing, what gaps exist, and where there’s room to grow.

    Why we did it: The Business Mix Analysis is crucial for understanding the current economic health of downtown Wheatley and identifying both strengths and areas for improvement. It pinpoints opportunities for growth and helps guide strategic business recruitment and development, ensuring that any new businesses address community needs and complement existing ones. This thorough analysis is key to fostering a vibrant and thriving downtown that meets the desires and requirements of our community.

    For detailed information, please refer to the full report: Wheatley Business Mix Analysis Full Report

Page last updated: 11 Nov 2024, 03:44 PM