Wheatley Updates
This page will act as a resource page for Wheatley's Revitalization project.
This page will act as a resource page for Wheatley's Revitalization project.
-
Work Proceeding on APEC 3
Work crews have completed driving a conductor pipe into the bedrock at the APEC 3 site at the northern end of the municipal parking lot.
The 13” pipe surrounds the actual well and material brought to the surface will be used to help determine the nature of the well.
Drilling work is finished, and cementing is scheduled for Thursday.
Work has already been completed on APEC 2 (also known as the Tait Well). Once APEC 3 is completed, remediation will begin on the APEC 1 well. (nearest the explosion site).
-
Talbot Road and Erie South Re-opened
Following the activation of street and traffic lights today, Talbot Road and Erie South have been re-opened. Fences were moved Monday.
The new emergency site map showing boundaries Is attached.
Operations on APEC 3 are underway, and work will continue through the week. A conductor pipe will be driven over the original well and residents may notice hammering sounds that are different from the work that was done on the APEC 2 well.
Property owners have had Orders placed on their buildings from the Chief Building Official. The Chief Building Official will be rescinding the orders on each property once Municipal Water (PUC), Electrical Authority (ESA), and Natural Gas (Enbridge) have been reinstated by the utility and an inspection by Building Development Services has taken place.
Upon reconnection of the utilities, property owners are to call 3-1-1 and ask to be directed to Building Development Services to schedule an inspection. It is expected that Building Development Services will complete this inspection within 24 hours of receiving the request.
-
Work has Progressed on Site
Work has progressed on site that will allow a further reduction to the Wheatley Emergency area. Fences will be moved Monday, May 30 for the properties along Talbot Road that are outside the area identified in purple, yellow and red hatched on the attached map.
Talbot Road and Erie Street South will remain closed and be re-opened as soon as they are deemed safe to allow through traffic. Local traffic will be permitted for property owners and tenants to start the recovery of their buildings.
Pleased be advised that property owners will have Orders placed on their buildings from the Chief Building Official. The Chief Building Official will be rescinding the orders on each property once Municipal Water (PUC), Electrical Authority (ESA) and Natural Gas (Enbridge) have been reinstated by the utility and an inspection by Building Development Services has taken place.
Upon reconnection of the utilities, property owners are to call 3-1-1 and ask to be directed to Building Development Services to schedule an inspection. It is expected that Building Development Services will complete this inspection within 24 hours of receiving the request.
For more details on the reasons for the Order, please refer to page 4 of the Resources and Information for Residents and Business – Building Owners document found, which can be found at:
https://www.letstalkchatham-kent.ca/wheatley-updates
Operations on APEC 3 well are underway, and work will continue through the weekend. A conductor pipe will be driven over the original well and residents may notice hammering sounds that are different from the work that was done on the APEC 2 well.
-
Plans Underway for Well and Road Work
Contractors are preparing to begin the next investigative step on the APEC 3 well at the far end of the municipal parking lot near the intersection of Erie and Elm Streets.
The investigation will determine whether the well was drilled for water or gas exploration and the findings will determine remediation steps.
Work is also underway to re-open Talbot Street East and West and Erie Street South. Those streets could be open early next week.
Advance voting for the June 2 provincial election which has been taking place at the Wheatley United Church, 59 Talbot Road concludes today at 8:00 pm. That same location will be the polling station on election day, June 2.
-
Evacuation Zone Will Be Reduced Again Tomorrow
As reported on May 14 during the Virtual Wheatley Town Hall Meeting, the evacuation zone is being reduced. The fence defining the northern boundary of the evacuation zone is being moved this week. Effective Friday, May 20 several residents on Elm St. Erie St. N. and Foster St. will have access to their properties. The following properties remain within the evacuation zone 34 Foster St., 47 Erie St. N. and 14 Elm St. Properties located along Talbot Trail that appear to be outside of the new reduced evacuation zone will remain inaccessible until Talbot Road opens to traffic.
Additional work is planned for next week that is needed for further reductions on the emergency zone to take place. Updates will be provided when the date of this additional work has been confirmed. Talbot Road will still remain closed to throughway traffic until the work is completed.
A copy of the map showing the new zone is available on Let’s Talk Chatham-Kent.
-
New Completion Deadline set for Wheatley Well Remediation
A tentative date for the completion of well remediation in Wheatley has been pushed back until the end of June.
During a virtual public meeting held on April 9 officials announced a reduction in the evacuation zone and provided a tentative goal of mid-to-late May for remediation of all Areas of Potential Environmental Concern (APEC) within the reduced zone.
Although capping has commenced on the Tait well (APEC 2) near the centre of the municipal parking lot, detailed work plans for similar work on APEC 1 (the well nearest the explosion site) and APEC 3 (the well at the far end of the municipal parking lot near the intersection of Erie and Elm streets) have yet to be completed.
Officials have said safety remains the utmost concern, noting that there were two significant releases of lower explosive limit (LEL) gas on April 22 and 23. In both cases, the systems, procedures and venting stack worked according to design.
Work on the wells will take longer than originally thought. The process of plugging a gas well is complex. Sometimes wells that were previously plugged require that they first be drilled out and re-plugged to ensure a proper seal of the well.
During the drilling process, various subsurface conditions could be encountered which help to inform how to proceed with the next steps and can result in changes to both timelines and the workplan.
The mitigation work requires expert consultation and methodical actions to ensure that health and safety is maintained while completing the work to current standards, involving modern construction techniques and materials.
Everyone on site is committed to working to resolve the issue as quickly as possible, while ensuring that the appropriate health and safety measures are taken throughout the course of the mitigation work, to protect the public and those working in and around the area.
The Tait/APEC 2 Well has been cemented/plugged up to the bedrock surface. Plugging activities at this well did take longer than expected which has pushed the overall project timeline out, however, the work on the Tait well is expected to be completed in the very near future. The team will then move to begin plugging activities on the APEC 3 Well and then to the APEC 1 Well.
This week the municipality sent notices to owners of some properties within the evacuation zone regarding possible structural damage and what steps would be needed for future occupancy.
The municipality will host a virtual meeting Saturday, May 14 at 10 am to answer residents' questions.
The meeting will be hosted on the municipality’s Facebook and YouTube channels.
-
New Completion Deadline set for Wheatley Well Remediation
A tentative date for the completion of well remediation in Wheatley has been pushed back until the end of June.
During a virtual public meeting held on April 9 officials announced a reduction in the evacuation zone and provided a tentative goal of mid-to-late May for remediation of all Areas of Potential Environmental Concern (APEC) within the reduced zone (see map).
Although capping has commenced on the Tait well (APEC 2) near the centre of the municipal parking lot, detailed work plans for similar work on APEC 1 (the well nearest the explosion site) and APEC 3 (the well at the far end of the municipal parking lot near the intersection of Erie and Elm streets) have yet to be completed.
Officials have said safety remains the utmost concern, noting that there were two significant releases of lower explosive limit (LEL) gas on April 22 and 23. In both cases, the systems, procedures and venting stack worked according to design.
This week the municipality sent notices to owners of some properties within the evacuation zone regarding possible structural damage and what steps would be needed for future occupancy.
The municipality will host a virtual meeting Saturday, May 14 at 10 am to answer residents' questions.
The meeting will be hosted on the Municipality's Facebook page and YouTube channels.
-
Preparations for Plugging Tait Well
The next step in remediation of the Tait Well in the municipal parking lot will begin during the coming week.
The project team is planning to use downhole charges to perforate the well casing.
This is being performed in order to create holes in the casing in order for the cement to reach all areas of the well as part of the plugging operations.
These are industry standard procedures that are routinely and safely used in the local oil and gas industry.
Any noise or vibration associated with the casing perforation is part of the site operations.
Chatham-Kent Fire and Emergency Services will continue its on-site presence.
-
Additional $3.9 Million Approved for Wheatley
The Municipality of Chatham-Kent has secured a further $3.9 million from the Ontario Ministry of Economic Development, Job Creation and Trade to support the community of Wheatley after the explosion in August of last year, bringing the total amount secured to $5.9 million.
Downtown Wheatley business owners and co-chairs of the BIA Mike and Erika Renwick said, "we are pleased to see this additional Provincial funding distributed. We appreciate the ongoing efforts of the Municipality’s Economic Development department in their communications surrounding the funding from the province. Our hope is that these additional funds will help to alleviate some of the continued financial hardships these businesses have endured and we look forward to the continued support of the province in regard to this."
To date, $1.97 million has been distributed amongst 30 businesses, four not-for-profit organizations and 19 commercial properties over the last several months, helping provide much-needed financial assistance while they are unable to operate.
“We’d like to thank the businesses of Wheatley for their patience, understanding, and tenacity during this difficult process. We’d also like to thank Premier Ford and his team for their diligent efforts to get these funds released into our community,” said Chatham-Kent Mayor Darrin Canniff. “This process has shown what can be accomplished when a fluid collaborative relationship is established between municipal and provincial government.”
The additional $3.9M is being distributed in three phases designed to assist the affected businesses with revenue losses up to August 2022, with the first disbursement taking place immediately to approved applicants.
“Our municipality has been focusing on doing everything we can to help the affected businesses of Wheatley. We’re thankful that the province of Ontario has been at the table working with us from day one and hopefully this additional $3.9 million will help the businesses during the time it takes to open their doors again,” said Stuart McFadden, Director of Economic Development Services.
Chatham-Kent Economic Development has been coordinating the process of fund disbursement to the displaced businesses and will continue to play a role in providing affected businesses with up-to-date information, guidance, and support.
-
Work on Wheatley Properties Under Way
The clean-up and restoration of utilities to properties formerly in the evacuation zone in Wheatley continues this week.
As of this morning, 14 customers have had their electricity restored and ten have had their water turned on. Three dumpsters have been placed outside the evacuation zone for the convenience of residents. At this time, residents are not being billed for water usage.
Portable washroom facilities have been made available for residents who are working on their properties but haven't had water restored.
Earlier this month, the evacuation zone was reduced. A map of the new zone can be found on Let's Talk Chatham-Kent/Wheatley-Updates.
Chatham-Kent Public Works Director Ryan Brown said officials are examining data from two incidents last week involving the release of a low level of combustible gas.
There was a release of gas Friday morning and a second release Friday night that lasted until Saturday morning. In both cases, the systems, procedures and venting stack worked according to design.
The last release at APEC 1 happened in November of 2021.
Brown said the incidents demonstrated the effectiveness of safety procedures in place and served as a reminder that the situation is not yet fully resolved.
Chatham-Kent Fire Chief Chris Case said Fire and Emergency Services provided additional resources and air monitoring around the perimeter of the evacuation zone to ensure safety.
"There are valid reasons why we have been on site non-stop since gas was detected last June," he said. "Although there was no threat to public safety on the weekend, we cannot let our guard down. We will remain in place until such time as the situation is resolved."
Wheatley Investigation Updates
Timeline
-
Hire Economic Development Officer (EDO)
Wheatley Updates has finished this stageMarch 2024
-
Trade Are Report Survey
Wheatley Updates has finished this stageApril - June 2024
-
Demolition of Buildings
Wheatley Updates has finished this stageMay - June 2024
-
Community Consultation #1
Wheatley Updates has finished this stageMay 25th 2024
-
Trade Area Report Analysis
Wheatley Updates has finished this stageJune 2024
-
Business Mix Analysis
Wheatley Updates has finished this stageJune 2024
-
Community Consultation #2
Wheatley Updates has finished this stageAugust 17th 2024
-
Conduct Research, Surveys & Gather Statistics
Wheatley Updates has finished this stageMay - September 2024
-
Seasonal Resident/Visitor Survey
Wheatley Updates has finished this stageMay - September 2024
-
Exploration Under Buildings
Wheatley Updates has finished this stageSeptember 2024
-
Coffee Chat with EDO
Wheatley Updates has finished this stageOctober 25th, 10AM at Lil Hil's
-
Drilling
Wheatley Updates has finished this stageOctober 2024
-
Drilling Equipment Moved Out
Wheatley Updates has finished this stageOctober 23rd, 2024
-
Downtown Business Revitalization Report Completed
Wheatley Updates has finished this stageOctober 30, 2024
-
Site Report Completed (Tentative)
Wheatley Updates has finished this stageNovember 30, 2024
-
Urban Visioning RFP Circulated
Wheatley Updates has finished this stageNovember/December 2024
-
Community Action Plan Completed
Wheatley Updates is currently at this stageJanaury 2025
-
Urban Visioning RFP Awarded
this is an upcoming stage for Wheatley UpdatesJanuary - February 2025
-
Community Action Plan Presented to Council
this is an upcoming stage for Wheatley UpdatesFebruary 2025
-
Urban Visioning Process to Begin
this is an upcoming stage for Wheatley UpdatesMarch 2025
Important Links
March 1 Meeting
Golder Report
-
GOLDER-WSP-Wheatley Pathways Report-Final (14.6 MB) (pdf)
-
Appendix A-Work Program(Final)_12Mar2023(Final Rprt Rev B-Pathways Analysis Wheatley Nat Gas Emis) (144 MB) (pdf)
-
Appendix B-Regional and Local Site Data(Final)_12Mar2023(Final Rprt Rev B-Pathways Analysis Wheatley Nat Gas Emis) (69.2 MB) (pdf)
-
Appendix C-Site Field Investigtn(Final)_12Mar2023(Final Rprt Rev B-Pathways Analysis Wheatley Nat Gas Emis) (40.8 MB) (pdf)
-
Appendix D-Bradco Well Abndmt Operat(Final)_12Mar2023(Final Rprt Rev B-Pathways Analysis Wheatley Nat Gas Emis) (1.45 MB) (pdf)
-
Appendix E-Geochemistry(Final)_12Mar2023(Final Rprt Rev B-Pathways Analysis Wheatley Nat Gas Emis) (23.5 MB) (pdf)
-
Appendix F-Limitations(Final)_12Mar2023(Final Rprt Rev B-Pathways Analysis Wheatley Nat Gas Emis) (214 KB) (pdf)
Hydrogen Sulfide Information
TL Watson Report
-
Appendix 1 - Recommendation for Emergency Evacuation Zone Reduction - November 25, 2022 (7.87 MB) (pdf)
-
Appendix 2 - BH Logs (538 KB) (pdf)
-
Appendix 3 - Well Information Package (2.82 MB) (pdf)
-
Appendix 4 - Memo July 6 Event (1.05 MB) (pdf)
-
Appendix 5 - Disposal Well Concerns (14.7 MB) (pdf)
-
Appendix 6 - Memo Oct 11, 2022 Flow Test (685 KB) (pdf)
-
Appendix 7 - Gas Well Test Sheet Wheatley (26.7 KB) (pdf)
-
Appendix 8 - Chatham-Kent Flow Test Report - November 27, 2022 (1.02 MB) (pdf)
-
Appendix 9 - Dispersion Modelling Report Wheatley Townsite Vent and Flare Assessment - November 26, 2022 (14.8 MB) (pdf)
-
Appendix 10 - Wheatley GM Surveys (948 KB) (pdf)
-
Appendix 11a - 8T Operations Manual - 2020 (1.78 MB) (pdf)
-
Appendix 11b - 320MAX Cut Sheet (31.9 KB) (pdf)
-
Wheatley Gas Emission Report - November 28, 2022 (7.17 MB) (pdf)
Reduced Evacuation Zone
Resources and Information for Wheatley Residents and Business - Building Owners
CRA Message and Information for Evacuated from Homes/Businesses
Current Images of Site
Who's Listening
-
Phone 519-360-1998 Email ck311@chatham-kent.ca -
Phone 519-360-1998 Email ckmayor@chatham-kent.ca
Documents & Applications
-
April 19, 2023 Test Report (19 MB) (pdf)
-
APEC Locations (854 KB) (pdf)
-
2021 Declaration State of Emergency Wheatley (1.06 MB) (pdf)
-
Wheatley Expenses - September 30 (175 KB) (pdf)
-
Letter to Insurers (550 KB) (pdf)
-
Wheatley BIA Disaster Relief Application Form (143 KB) (pdf)
-
Wheatley Business Support Program Application (349 KB) (pdf)
-
Wheatley Residents Assistance Program FAQs (29.1 KB) (pdf)
-
Wheatley Residents Assistance Program Update to Guidelines (35.7 KB) (pdf)
-
February 5 2024 Council Meeting: Acquisition of Property
-
Wheatley Preliminary Report Jan 10 2025.pdf (85.7 MB) (pdf)