Council has approved the next step in the process to construct a Transitional Housing Program on the corner lot of Hyslop St. and Park St. in Chatham.
Update - March 13 2025:
Henry Heyink Construction Ltd.- Site services
Grading is being completed – as weather permits.
Electrical cables installation is due to start after pile foundation are completed.
Site was setup with proper construction safety fence. Approved by Project Contract administrator and CK representative (Kokil Agarwal)
Site Removals & excavations – completed.
Jayden Construction – Cabins – supply and install
Cabin Building permit – Received.
Helical Piles foundation work scheduled to begin Last week of March
Delivery of cabins – expected – 1st week of April.
Install of Cabins to begin – 3rd week of April.
At the October 21st, 2024 council meeting, Jayden Construction was awarded the contract for the construction of the project. Site development work is now underway and the project is on target for completion by the June 2025 deadline.
Key facts:
In April 2020, the Municipality of Chatham-Kent opened a temporary emergency shelter in response to the increasing numbers of individuals and families falling into homelessness due to the COVID-19 pandemic.
Since this time the number of people experiencing homelessness has continued to increase despite Municipal and community efforts to assist those in need.
Recognizing the need for shelter was not decreasing, Council directed administration to provide a recommendation on future emergency/transitional housing plans.
In January 2024, Council provided approval to administration to move forward with the Transitional Cabin Program, which will replace the existing emergency shelter
The report titled “Emergency Transitional Cabin Program Location” outlines next steps in the process, which are as follows:
Pre-site development work including drawings and site servicing
Hire a Project Manager to assist with this project as well as other current and future municipal affordable housing developments
Issuing a Request for Proposal (RFP) for the construction of the project
Issuing an RFP for 24/7 security services for the future location
This page will be continuously updated as the project moves forward.
Council has approved the next step in the process to construct a Transitional Housing Program on the corner lot of Hyslop St. and Park St. in Chatham.
Update - March 13 2025:
Henry Heyink Construction Ltd.- Site services
Grading is being completed – as weather permits.
Electrical cables installation is due to start after pile foundation are completed.
Site was setup with proper construction safety fence. Approved by Project Contract administrator and CK representative (Kokil Agarwal)
Site Removals & excavations – completed.
Jayden Construction – Cabins – supply and install
Cabin Building permit – Received.
Helical Piles foundation work scheduled to begin Last week of March
Delivery of cabins – expected – 1st week of April.
Install of Cabins to begin – 3rd week of April.
At the October 21st, 2024 council meeting, Jayden Construction was awarded the contract for the construction of the project. Site development work is now underway and the project is on target for completion by the June 2025 deadline.
Key facts:
In April 2020, the Municipality of Chatham-Kent opened a temporary emergency shelter in response to the increasing numbers of individuals and families falling into homelessness due to the COVID-19 pandemic.
Since this time the number of people experiencing homelessness has continued to increase despite Municipal and community efforts to assist those in need.
Recognizing the need for shelter was not decreasing, Council directed administration to provide a recommendation on future emergency/transitional housing plans.
In January 2024, Council provided approval to administration to move forward with the Transitional Cabin Program, which will replace the existing emergency shelter
The report titled “Emergency Transitional Cabin Program Location” outlines next steps in the process, which are as follows:
Pre-site development work including drawings and site servicing
Hire a Project Manager to assist with this project as well as other current and future municipal affordable housing developments
Issuing a Request for Proposal (RFP) for the construction of the project
Issuing an RFP for 24/7 security services for the future location
This page will be continuously updated as the project moves forward.