Update on 99 McNaughton returns
Work continues daily on 99 McNaughton. At this time, in order to allow for a smooth return for tenants living in section D, the official move in date will be Monday November 18th, 2024. Three additional days are needed to ensure a safe return. Staff will be reaching out to impacted tenants closer to November 15th to discuss options and to share more on what to expect.
For tenants who were displaced from Section C, staff do not have a specific date at this time but have been advised that all tenants in section C can expect to be home before December 24th, 2024. As work progresses, staff will provide additional updates on Let’s Talk.