Wheatley Updates
This page will act as a resource page for Wheatley's Revitalization project.
This page will act as a resource page for Wheatley's Revitalization project.
-
Remediation at APEC 1 Site Expected to Resume Next Week
Additional testing at the APEC 1 one site will push back remediation efforts until next week.
Work crews are examining several procedures related to how to best cap the well.
Work had been expected to resume Friday, however, additional time is needed to before entering the next phase due to the testing.
When work resumes, an odour of gas may be detected. If residents at any time detect the smell of gas, they are asked to immediately call 9-1-1.
-
Work was Paused at the APEC 1
Work was paused at the APEC 1 site while crews prepare to do additional testing following last Wednesday’s gas release.
The two-hour release was measured at 24 parts per billion in the atmosphere, less than one-hundredth of the amount that would represent a safety hazard. Some smell was noticeable at the site.
There has been no gas emission since that time.A thorough review of the gas monitoring system and health and safety plans confirmed that no further action is required.
Work is expected to resume by the end of the week at which time an odour of gas may be detected. If residents at any time detect the smell of gas, they are asked to immediately call 9-1-1.
Workers were in the process of excavating around the well in preparation for driving a larger conductor pipe over the existing well when the release occurred.
At the time Chatham-Kent Fire Chief Chris Case confirmed that the safety plans guiding the operations worked as planned. “Gas was collected and directed to the vent to be flared. At no time was there a risk to our community located beyond the evacuation zone.”
-
Gas Release Reported at APEC 1 Site
At approximately 3 p.m. Wednesday, monitoring systems picked up a release of gas while crews were working at the APEC 1 site.
Work stopped and samples of the gas were taken for analysis.
At approximately 5 p.m. the release of gas ended.
Officials are gathering and reviewing data to determine when work can resume.
Workers were in the process of excavating around the well in preparation for driving a larger conductor pipe over the existing well when the release occurred.
Chatham-Kent Fire Chief Chris Case confirmed that the safety plans guiding the operations worked as planned. “Gas was collected and directed to the vent to be flared. At no time was there a risk to our community located beyond the evacuation zone.”
Chief Case noted that a sufficient amount of gas was present for those nearby to detect a smell. He noted that instruments detected 24 parts per billion in the atmosphere, less than one-hundredth of the amount that would represent a safety hazard.
-
Additional Equipment has Arrived On-site
Additional equipment has arrived on-site and work crews will start the process of driving a larger conductor pipe over the existing APEC 1 well.
The initial work completed on the well indicates it is approximately 100 feet deep and was most likely constructed as a source of water.
Once the pipe-driving is completed, remediation will begin. It is estimated that drilling and remediation will be completed during the next two to three weeks.
No gas has been detected so far throughout the process, however, the team will sample for analysis if this changes.
-
Awaiting Additional Equipment
Work crews are awaiting additional equipment to continue coring the APEC 1 well nearest the site of last year’s explosion. Work on the well started this week.
The intent of this work is to learn more about the construction and depth of this well. No gas has been detected throughout the process.
Work has been paused until additional equipment arrives on site. The equipment is expected to be on-site Monday.
Once the investigation is complete the activities will switch over to remediation on APEC 1.
A total of 58 properties, residential or commercial have been affected by the reductions in the evacuation area. Each of those properties was deemed unsafe by Building Development Services and orders prohibiting use or occupancy were issued.
To date, orders on 15 residential and 6 commercial properties have been rescinded which allows those property owners to move back into their homes or open their businesses.
Of the 34 homeowners who were evacuated after the explosion, 10 homeowners, have returned home with another expected shortly.
-
Work begins on APEC 1
Work crews Monday began coring of the APEC 1 well nearest the site of last year’s explosion. The intent of this work is to learn more about the construction and depth of this well. No gas has been detected throughout the process.
Work is continuing today, and residents may see more activity and heavy equipment on-site in the coming days. Once the investigation is complete the activities will switch over to remediation on APEC 1.
-
Work Completed on APEC 3
Work crews have completed driving a conductor pipe into the bedrock at the APEC 3 site at the northern end of the municipal parking lot.
Work will begin on APEC 1 early next week.
Work has already been completed on APEC 2 (also known as the Tait Well).
Wheatley team will be coordinating request from those still evacuated up until the work starts.
-
Work Proceeding on APEC 3
Work crews have completed driving a conductor pipe into the bedrock at the APEC 3 site at the northern end of the municipal parking lot.
The 13” pipe surrounds the actual well and material brought to the surface will be used to help determine the nature of the well.
Drilling work is finished, and cementing is scheduled for Thursday.
Work has already been completed on APEC 2 (also known as the Tait Well). Once APEC 3 is completed, remediation will begin on the APEC 1 well. (nearest the explosion site).
-
Talbot Road and Erie South Re-opened
Following the activation of street and traffic lights today, Talbot Road and Erie South have been re-opened. Fences were moved Monday.
The new emergency site map showing boundaries Is attached.
Operations on APEC 3 are underway, and work will continue through the week. A conductor pipe will be driven over the original well and residents may notice hammering sounds that are different from the work that was done on the APEC 2 well.
Property owners have had Orders placed on their buildings from the Chief Building Official. The Chief Building Official will be rescinding the orders on each property once Municipal Water (PUC), Electrical Authority (ESA), and Natural Gas (Enbridge) have been reinstated by the utility and an inspection by Building Development Services has taken place.
Upon reconnection of the utilities, property owners are to call 3-1-1 and ask to be directed to Building Development Services to schedule an inspection. It is expected that Building Development Services will complete this inspection within 24 hours of receiving the request.
-
Work has Progressed on Site
Work has progressed on site that will allow a further reduction to the Wheatley Emergency area. Fences will be moved Monday, May 30 for the properties along Talbot Road that are outside the area identified in purple, yellow and red hatched on the attached map.
Talbot Road and Erie Street South will remain closed and be re-opened as soon as they are deemed safe to allow through traffic. Local traffic will be permitted for property owners and tenants to start the recovery of their buildings.
Pleased be advised that property owners will have Orders placed on their buildings from the Chief Building Official. The Chief Building Official will be rescinding the orders on each property once Municipal Water (PUC), Electrical Authority (ESA) and Natural Gas (Enbridge) have been reinstated by the utility and an inspection by Building Development Services has taken place.
Upon reconnection of the utilities, property owners are to call 3-1-1 and ask to be directed to Building Development Services to schedule an inspection. It is expected that Building Development Services will complete this inspection within 24 hours of receiving the request.
For more details on the reasons for the Order, please refer to page 4 of the Resources and Information for Residents and Business – Building Owners document found, which can be found at:
https://www.letstalkchatham-kent.ca/wheatley-updates
Operations on APEC 3 well are underway, and work will continue through the weekend. A conductor pipe will be driven over the original well and residents may notice hammering sounds that are different from the work that was done on the APEC 2 well.
Wheatley Investigation Updates
Timeline
-
Hire Economic Development Officer (EDO)
Wheatley Updates has finished this stageMarch 2024
-
Trade Are Report Survey
Wheatley Updates has finished this stageApril - June 2024
-
Demolition of Buildings
Wheatley Updates has finished this stageMay - June 2024
-
Community Consultation #1
Wheatley Updates has finished this stageMay 25th 2024
-
Trade Area Report Analysis
Wheatley Updates has finished this stageJune 2024
-
Business Mix Analysis
Wheatley Updates has finished this stageJune 2024
-
Community Consultation #2
Wheatley Updates has finished this stageAugust 17th 2024
-
Conduct Research, Surveys & Gather Statistics
Wheatley Updates has finished this stageMay - September 2024
-
Seasonal Resident/Visitor Survey
Wheatley Updates has finished this stageMay - September 2024
-
Exploration Under Buildings
Wheatley Updates has finished this stageSeptember 2024
-
Coffee Chat with EDO
Wheatley Updates has finished this stageOctober 25th, 10AM at Lil Hil's
-
Drilling
Wheatley Updates has finished this stageOctober 2024
-
Drilling Equipment Moved Out
Wheatley Updates has finished this stageOctober 23rd, 2024
-
Downtown Business Revitalization Report Completed
Wheatley Updates has finished this stageOctober 30, 2024
-
Site Report Completed (Tentative)
Wheatley Updates is currently at this stageNovember 30, 2024
-
Urban Visioning RFP Circulated
this is an upcoming stage for Wheatley UpdatesNovember/December 2024
-
Community Action Plan Completed
this is an upcoming stage for Wheatley UpdatesJanaury 2025
-
Urban Visioning RFP Awarded
this is an upcoming stage for Wheatley UpdatesJanuary - February 2025
-
Community Action Plan Presented to Council
this is an upcoming stage for Wheatley UpdatesFebruary 2025
-
Urban Visioning Process to Begin
this is an upcoming stage for Wheatley UpdatesMarch 2025
Important Links
March 1 Meeting
Golder Report
- GOLDER-WSP-Wheatley Pathways Report-Final (14.6 MB) (pdf)
- Appendix A-Work Program(Final)_12Mar2023(Final Rprt Rev B-Pathways Analysis Wheatley Nat Gas Emis) (144 MB) (pdf)
- Appendix B-Regional and Local Site Data(Final)_12Mar2023(Final Rprt Rev B-Pathways Analysis Wheatley Nat Gas Emis) (69.2 MB) (pdf)
- Appendix C-Site Field Investigtn(Final)_12Mar2023(Final Rprt Rev B-Pathways Analysis Wheatley Nat Gas Emis) (40.8 MB) (pdf)
- Appendix D-Bradco Well Abndmt Operat(Final)_12Mar2023(Final Rprt Rev B-Pathways Analysis Wheatley Nat Gas Emis) (1.45 MB) (pdf)
- Appendix E-Geochemistry(Final)_12Mar2023(Final Rprt Rev B-Pathways Analysis Wheatley Nat Gas Emis) (23.5 MB) (pdf)
- Appendix F-Limitations(Final)_12Mar2023(Final Rprt Rev B-Pathways Analysis Wheatley Nat Gas Emis) (214 KB) (pdf)
Hydrogen Sulfide Information
TL Watson Report
- Appendix 1 - Recommendation for Emergency Evacuation Zone Reduction - November 25, 2022 (7.87 MB) (pdf)
- Appendix 2 - BH Logs (538 KB) (pdf)
- Appendix 3 - Well Information Package (2.82 MB) (pdf)
- Appendix 4 - Memo July 6 Event (1.05 MB) (pdf)
- Appendix 5 - Disposal Well Concerns (14.7 MB) (pdf)
- Appendix 6 - Memo Oct 11, 2022 Flow Test (685 KB) (pdf)
- Appendix 7 - Gas Well Test Sheet Wheatley (26.7 KB) (pdf)
- Appendix 8 - Chatham-Kent Flow Test Report - November 27, 2022 (1.02 MB) (pdf)
- Appendix 9 - Dispersion Modelling Report Wheatley Townsite Vent and Flare Assessment - November 26, 2022 (14.8 MB) (pdf)
- Appendix 10 - Wheatley GM Surveys (948 KB) (pdf)
- Appendix 11a - 8T Operations Manual - 2020 (1.78 MB) (pdf)
- Appendix 11b - 320MAX Cut Sheet (31.9 KB) (pdf)
- Wheatley Gas Emission Report - November 28, 2022 (7.17 MB) (pdf)
Reduced Evacuation Zone
Resources and Information for Wheatley Residents and Business - Building Owners
CRA Message and Information for Evacuated from Homes/Businesses
Current Images of Site
Who's Listening
-
Phone 519-360-1998 Email ck311@chatham-kent.ca -
Phone 519-360-1998 Email ckmayor@chatham-kent.ca
Documents & Applications
- April 19, 2023 Test Report (19 MB) (pdf)
- APEC Locations (854 KB) (pdf)
- 2021 Declaration State of Emergency Wheatley (1.06 MB) (pdf)
- Wheatley Expenses - September 30 (175 KB) (pdf)
- Letter to Insurers (550 KB) (pdf)
- Wheatley BIA Disaster Relief Application Form (143 KB) (pdf)
- Wheatley Business Support Program Application (349 KB) (pdf)
- Wheatley Residents Assistance Program FAQs (29.1 KB) (pdf)
- Wheatley Residents Assistance Program Update to Guidelines (35.7 KB) (pdf)
- February 5 2024 Council Meeting: Acquisition of Property